Case Study

Bessakerfjellet Wind farm

Bessakerfjellet Wind farm
  • LOCATION
    Norway
  • PARTNERSHIP
    TrønderEnergi

Project description:

  • The Bessakerfjellet wind farm comprises the areas of Mehøgda, Storhøgda and Blåfjellet in Roan municipality in the county of Sør-Trøndelag.
  • The installation consists of 25 wind turbines, each with an output of 2.3 MW. Average annual production is estimated at 176 GWh.


Customer’s challenges:

  • The customer required a complete solution with specially adapted unspliced TSLF-O 24 kV cable lengths, from the secondary station to the turbines and between the turbines.
  • The distance between the turbines is approximately 200 to 300 metres.
  • A potential need for fibre to be blown in at a later date.


Nexans’ solutions:

  • In order to reduce costs, each length and drum were uniquely marked to ensure simple and efficient progress in the project.
  • The wind farm is managed remotely from TrønderEnergi’s control centre via fibre cables that were blown into the TSLF-O cables, the three power phases having been twisted along with three empty tubes in the spaces between the twists to allow the future blowing of fibre cables.

 

Contáctanos

Temas sobre los que desea recibir mayor información

Campos requeridos

Por favor revise la data ingresada e intente nuevamente

El correo debe contener este símbolo @

Protección de data personal

Tiene el derecho de rechazar el procesamiento de sus datos personales y/o su uso para propósitos comerciales

¡Gracias!

Gracias por contactarse con nosotros. Nos pondremos en contacto pronto.

Error

Ocurrió un error. Por favor intentar nuevamente

Cerrar